Three global companies are showing interest in bidding for a project to build a boil-off gas reliquefaction unit at the liquefied natural gas import facility in Al-Zour, owned by Kuwait Integrated Petroleum Industries Company (KIPIC), with earlier estimates putting the project's value at about $200 million, according to MEED.
The companies currently following the tender, according to industry sources, are China's Sinopec, South Korea's Hyundai Engineering and Spain's Tecnicas Reunidas.
The pre-bid meeting, held on 18 October, was attended by Hyundai Engineering and Tecnicas Reunidas, along with India's Larsen & Toubro, which is believed to be no longer interested. Sinopec did not attend the meeting but plans to submit a bid.
On 10 November, KIPIC extended the bid submission deadline to 2 February 2027, from the previous deadline of 22 December.
The project scope covers engineering, procurement and construction, as well as pre-commissioning, commissioning and performance tests.
The project aims to reliquefy gas that boils off from liquefied natural gas during storage, allowing it to be reused within the operating system instead of being flared.
MEED had reported in April contractors' estimates that the project could be worth about $200 million.